PM Community

Questions, insights, and achievements from project managers worldwide.

System·7/8/2026question

When to use hybrid vs pure agile vs predictive?

The PMP exam seems to expect us to know when each approach is appropriate. What are the deciding factors? Is there a decision framework?

16 votes 0 replies
agilehybridpredictive
System·7/8/2026question

When should you AVOID a risk vs MITIGATE it?

I understand avoidance eliminates the risk and mitigation reduces probability/impact. But in practice, how do you decide? If a risk has 80% probability and high impact, is that avoidance or mitigation territory?

11 votes 1 replies
risk-managementrisk-responsestrategies
System·7/8/2026question

What's the difference between a risk and an issue?

My team keeps logging risks that have already happened. Isn't that an issue, not a risk? Where's the line?

6 votes 0 replies
risk-managementissuesdefinitions
System·7/8/2026question

What's the difference between EAC formulas?

PMBOK lists 4 EAC formulas: BAC/CPI, AC + (BAC-EV), AC + bottom-up ETC, and AC + (BAC-EV)/(CPI*SPI). When do you use each one? I keep getting different answers on practice exams.

27 votes 1 replies
evmeacformulas
System·7/8/2026question

What does 'servant leadership' look like in exam questions?

Every practice exam has servant leadership questions and I keep picking the 'directive' answer when I should pick 'facilitative.' Can someone explain the pattern?

19 votes 0 replies
exam-strategyservant-leadershipagile
System·7/8/2026question

Velocity fluctuates wildly — is that normal?

Our team velocity goes 20, 35, 15, 28, 40 across sprints. Management says 'velocity should stabilize.' When does it? What's causing the swings?

21 votes 0 replies
agilevelocitymetrics
System·7/8/2026question

Trick questions: 'What should the PM do FIRST?'

These 'what should you do first' questions trip me up. Is it always 'review the project management plan' or 'consult the change control process'? Is there a framework?

10 votes 0 replies
exam-strategypmp-examprioritization
System·7/8/2026question

TCPI formula — when to use BAC vs EAC?

The TCPI formula is (BAC-EV)/(BAC-AC) or (BAC-EV)/(EAC-AC). My study guide says to use EAC when 'the original budget is no longer viable.' What does that mean in practice?

11 votes 0 replies
evmtcpiformulas
System·7/8/2026question

Should I memorize all the ITTOs?

My study group says 'don't memorize ITTOs, understand the flow.' But some practice questions literally ask which tool goes with which process. What's the right balance?

20 votes 0 replies
exam-strategyittostudy-tips
System·7/8/2026question

Secondary risks from risk responses — real example?

PMBOK mentions that risk responses can create secondary risks. Can someone give me a real-world example of this happening? I can't picture it.

19 votes 0 replies
risk-managementsecondary-risksexamples
System·7/8/2026question

Product Owner vs Sponsor — who has final say on scope?

In our Scrum project, the PO manages the backlog but the sponsor funds the project. When they disagree on priorities, who wins? PMBOK seems ambiguous on this.

8 votes 0 replies
agileproduct-ownersponsor
System·7/8/2026question

PMP exam: predictive vs agile question ratio?

I've heard the 2026 exam is 50/50 predictive and agile. Others say it's more like 60/40 agile-heavy. What should I focus my study time on?

20 votes 0 replies
exam-strategypmp-examagile
System·7/8/2026question

How to handle 'best answer' questions when two seem right?

On practice exams, I keep narrowing down to two options that both seem correct. I pick wrong 60% of the time. Is there a strategy for these?

10 votes 1 replies
exam-strategypmp-examtips
System·7/8/2026question

How to explain EVM to non-technical stakeholders?

My sponsor keeps asking 'are we on budget?' and I respond with CPI/SPI numbers and their eyes glaze over. What's the best way to communicate EVM data to executives?

5 votes 0 replies
evmcommunicationstakeholders
System·7/8/2026question

How often should the risk register be updated?

Our risk register has 45 risks, last updated 3 months ago. The PM says 'we review risks at milestones.' Is that enough? What does PMBOK recommend?

11 votes 0 replies
risk-managementmonitoringbest-practices
System·7/8/2026question

How do you handle fixed-scope contracts in agile?

Our client signed a fixed-scope contract but wants us to use Scrum. The scope is locked but we need to be flexible. Is this even possible? What approach works?

5 votes 0 replies
agilecontractsprocurement
System·7/8/2026question

How do I interpret a CPI of 0.85?

My project has a CPI of 0.85 after month 3. The PM says we're 'slightly over budget' but I think it's worse than that. How should I interpret this number and what should I tell the sponsor?

10 votes 1 replies
evmcost-managementcpi
System·7/8/2026question

Expected Monetary Value — do I add or multiply?

EMV = Probability x Impact. But in a decision tree with multiple branches, do I add the EMVs together? And are opportunity EMVs positive or negative?

24 votes 0 replies
risk-managementemvdecision-tree
System·7/8/2026question

Can you use earned value in Scrum?

My organization wants EVM reporting but we run Scrum. Story points don't map to dollars. Is there a way to make this work or should I push back?

25 votes 1 replies
agileevmscrum
System·7/8/2026question

Can SPI be greater than 1.0 but project still late?

My SPI is 1.05 which means ahead of schedule. But the critical path shows we're 2 weeks behind. How is this possible?

21 votes 0 replies
evmspicritical-path

Join the PM Community

Get your verified competency score, ask questions, share insights.

Join Free

Community

Members10
Posts20